Sample Residential Project Schedule
Meet with the owner to review project: 3-4 weeks.
Prepare schematic design for review and approval by owner: 2-3 weeks.
Preparation of construction documents (drawings, specifications, calculations and energy analysis): 4-8 weeks.
Code review and building permits: 4-6 weeks.
Bidding and contractor selection: 3-4 weeks.
Construction phase: 26-52 weeks.
This sample schedule reflects a typical minimum time line and is provided here to assist potential clients with early planning; however,all scheduling is highly variable and dependent on how quickly project information can be obtained from owners, the review workload of local authorities, contractor's schedule, and weather.